What DORA Article 28(8) and the contractual-policy RTS require in an exit strategy and exit plan for an ICT service such as a core banking system: scenarios, alternatives, transition, testing, the register fields, and a CSV template.
What does a DORA exit strategy for an ICT third-party provider have to cover?
A financial entity must have an exit strategy for every ICT service that supports a critical or important function, and a documented, tested exit plan behind it. The duty sits in Article 28(8) of Regulation (EU) 2022/2554 (DORA) and sits with the financial entity. The provider carries duties only through the contract. A core banking system delivered as a service is the usual example: if the vendor fails, the bank still has to keep accounts running. This note walks through what the plan has to contain, which provision asks for each part, and where the supervisor first sees whether a plan exists.
Status as of 22 November 2026: DORA has applied since 17 January 2025. We found no amendment to Article 28(8) or to Article 10 of the policy RTS, and no public enforcement decision about missing exit plans.
Which provisions sit behind an exit plan?
Four instruments work together, and they answer different questions.
| Instrument | What it adds |
|---|---|
| DORA Article 28(8) | The duty: exit strategies, risk scenarios, exit without disruption, documented and tested plans, transition plans, contingency measures |
| DORA Article 30(2)(d) and 30(3)(f) | The contract: return of data, and a mandatory adequate transition period for critical or important functions |
| Delegated Regulation (EU) 2024/1773, Article 10 | The policy: a documented exit plan for each contractual arrangement, with periodic review and testing |
| Implementing Regulation (EU) 2024/2956, B_07.01 | The register: whether a plan exists, how hard the provider is to replace, whether alternatives are identified |
The exit strategy is the entity’s decision on how it would leave a provider and in which circumstances. The exit plan is the executable document for one arrangement. RTS Article 10 asks the entity’s policy to require that plan for each contractual arrangement on ICT services supporting critical or important functions, and to cover its review and testing.
Which risks must the strategy take into account?
Article 28(8) lists risks at provider level: failure of the provider, deterioration of service quality, business disruption from inappropriate or failed provision, a material risk to the continuous deployment of the service, and termination in any of the circumstances of Article 28(7). The entity must be able to exit without disrupting its business, without limiting its compliance with regulatory requirements, and without harming the continuity and quality of the services it gives clients.
Article 28(7) lists four termination grounds that the contract has to allow:
- a significant breach by the provider of laws, regulations or contract terms;
- circumstances found through monitoring that could alter the performance of the service, including material changes to the arrangement or to the provider’s situation;
- evidenced weaknesses in the provider’s ICT risk management, in particular in the availability, authenticity, integrity and confidentiality of data;
- a situation in which the competent authority can no longer supervise the entity effectively because of the arrangement.
Each ground should map to a path in the plan. A bank that has a termination right for weak data security but no scenario for using it has a clause and no plan.
What must an exit plan contain?
The checklist below is built only from the provisions above. The first column is a part of the plan and the second is the provision that asks for it.
| Part of the plan | Provision |
|---|---|
| One documented plan for each arrangement supporting a critical or important function | RTS 2024/1773 Art. 10 |
| Scenarios: provider failure, quality deterioration, failed provision, persistent interruption, unexpected termination, each Art. 28(7) ground | DORA Art. 28(8); RTS Art. 10 |
| Alternative solutions: other providers or an in-house option | DORA Art. 28(8); register B_07.01.0110 and 0120 |
| Transition plan: removing the services and the data from the provider and transferring them securely and completely | DORA Art. 28(8) |
| Data: access, recovery and return in an easily accessible format | DORA Art. 30(2)(d) |
| Transition period during which the provider keeps delivering | DORA Art. 30(3)(f) |
| Implementation schedule that fits the exit and termination terms of the contract, including notice periods | RTS Art. 10; register B_02.02.0100 and 0110 |
| Realistic, feasible plan built on plausible scenarios and reasonable assumptions | RTS Art. 10 |
| Testing and periodic review | DORA Art. 28(8); RTS Art. 10 |
| Contingency measures that keep the business running during the exit | DORA Art. 28(8) |
| Register entry: exit plan Yes or No, substitutability, reintegration | Register B_07.01 |
The same list is available as a spreadsheet with an example row for each line: DORA exit plan template (CSV). The rows are generic examples with no real names. Replace them with your own arrangement, owner and review dates.
EBA guidance adds items for outsourcing in general: a business impact analysis of the people, money and time needed, assigned roles, success criteria and indicators that trigger the exit (EBA/GL/2019/02, paragraphs 106 to 108). These are not DORA requirements for ICT services, but they are sensible headings for a plan and the template lists them separately.
What does the contract have to say about leaving?
Three clauses carry most of the weight. Article 30(2)(d) requires every ICT contract to provide for access to data, its recovery and its return in an easily accessible format if the provider becomes insolvent, is resolved, discontinues its business or the contract ends. DORA gives no more detail on the format than that, so a promise to export “all data in a standard format” should be checked against what the plan needs on the day. Article 30(2)(h) requires termination rights and minimum notice periods. Article 30(3)(f), for critical or important functions, requires an exit strategy with a mandatory adequate transition period: the provider continues to deliver the service to reduce the risk of disruption or to support resolution and restructuring, and the period must allow migration to another provider or to in-house solutions in line with the complexity of the service.
No minimum period is set. The plan should state the entity’s own estimate of the time needed and compare it with the contractual period.
What does the plan look like for a core banking system?
The legal text is generic, so here is a worked example. The following is a general illustration, not a description of any vendor’s tooling. A payment institution runs its ledger on a vendor-operated core banking service. Its plan for that arrangement could contain:
- Data scope. Customer and account records, the balance history, postings and their audit trail, the product and fee configuration, and the interfaces that connect the ledger to payment schemes.
- Return of data. The format in which the vendor hands back each of these, and how fast, taken from the Article 30(2)(d) clause.
- Alternative. A second platform or an in-house build, with a note on what each would need before it could take over.
- Cut-over. How opening balances are loaded into the new system and reconciled against the old one, and how long both systems run in parallel.
- Transition period. How long the vendor keeps the old service running, set against the migration time the previous points imply.
- Contingency. What the business does while the switch happens, for example manual limits on payments.
The deployment model changes the plan. With a multi-tenant service run by the vendor, exit depends on the vendor’s export and on the transition period. Where the entity runs the software itself, on premise or in a private cloud, the data and infrastructure already sit inside its own boundary, and the plan concentrates on the software licence and on the skills needed to keep operating it. Corebanq is offered under three models: Cloud SaaS (multi-tenant managed deployment on Finray-managed infrastructure), Private SaaS (single-tenant cloud with dedicated infrastructure) and Enterprise Licence (on-premise or private-cloud deployment); the Corebanq deployment section describes each, and the deployment topology radar compares the regulatory questions each one raises, exit among them. For the tenancy question itself, see single-tenant versus multi-tenant core banking.
What does the supervisor see in the register of information?
The register is where a supervisor first learns whether a plan exists. In Implementing Regulation 2024/2956, template B_07.01 has these exit-related fields for each provider and ICT service:
| Field | Content |
|---|---|
| B_07.01.0050 | Substitutability of the provider (not substitutable, highly complex, medium complexity, easily substitutable) |
| B_07.01.0060 | Reason where the provider is not or hardly substitutable |
| B_07.01.0080 | Existence of an exit plan (Yes or No) |
| B_07.01.0090 | Possibility of reintegration of the service (easy, difficult, highly complex) |
| B_07.01.0100 | Impact of discontinuing the service |
| B_07.01.0110 | Whether alternative providers are identified |
| B_07.01.0120 | Identification of the alternative provider |
Template B_02.02 holds the notice period for the entity (0100) and for the provider (0110). A register that says “Yes” at 0080 and “Not substitutable” at 0050 invites the question of what the plan does about it. The field-by-field map is in the DORA RTS/ITS pack, and the filing channels are in the register of information tracker.
How often does the plan need testing?
Article 28(8) says plans must be sufficiently tested and reviewed periodically, in line with the proportionality criteria of Article 4(2). RTS Article 10 repeats the periodic review and testing. We did not find a supervisory statement that defines “sufficiently tested”, so the entity has to justify its own approach: a tabletop exercise on the provider-failure scenario, a restore of exported data into a test environment, and a review whenever the contract, the provider or the function changes are all reasonable steps to record. Record the date and result of each test next to the plan.
Who has to do this, and how does proportionality apply?
DORA covers 20 types of financial entity, including payment institutions, e-money institutions, account information service providers and MiCA-authorised crypto-asset service providers. Payment and e-money institutions that are exempted under PSD2 or the E-Money Directive follow the simplified ICT risk management framework of Article 16 and fall outside the written third-party strategy and policy duty of Article 28(2), which also does not apply to microenterprises. A microenterprise has fewer than 10 employees and a turnover or balance sheet total of no more than EUR 2 million. Article 28(8) itself carries no size exemption, and proportionality shapes its testing duty.
ICT third-party providers are not financial entities under DORA. A SaaS vendor’s duties therefore arise through the contract and, only if the ESAs designate it as a critical provider, through oversight under Article 31. DORA is EU law and applies to UK firms only through their EU entities.
What are the Swiss and EBA parallels?
FINMA Circular 2018/3 asks supervised institutions to provide for insourcing or an orderly transfer to another provider (margin no. 18.1); institutions with a licence under Article 1b of the Banking Act are exempt from the insourcing limb. The 2019 EBA outsourcing guidelines ask for a documented exit strategy for critical or important functions. The EBA published new guidelines on third-party risk for non-ICT services on 18 September 2026 (EBA/GL/2026/09); they are not yet applicable and leave ICT services to DORA.
Where does Ordinis fit?
An exit plan is a controlled document with owners, review dates and test evidence. Ordinis provides control inventory and evidence capture, and Ordinis exports the DORA register of information. Why DORA, not NIS2, governs a financial entity’s ICT risk is explained in DORA vs NIS2. The exit plan is one of the duties set out in ICT third-party risk management under DORA, and the B_07.01 fields sit in the DORA register of information with the other templates. For the product context on payment and e-money institutions, see solutions for payment and e-money institutions and the trust and due-diligence pack.
Frequently asked questions
- Which DORA article requires an exit strategy?
- Article 28(8), for ICT services that support critical or important functions. Article 30(3)(f) adds that the contract for such services must include exit strategies, in particular an adequate mandatory transition period during which the provider keeps delivering the service.
- Is one exit plan per provider enough?
- The RTS on the contractual policy (Delegated Regulation 2024/1773, Article 10) asks for a documented exit plan for each contractual arrangement that supports a critical or important function. A provider with two such contracts therefore needs two plans, which can share common sections.
- Does the plan have to be tested?
- Yes. Article 28(8) says exit plans must be sufficiently tested and periodically reviewed in line with the proportionality criteria of Article 4(2), and RTS Article 10 asks for periodic review and testing. We found no supervisory text that says what counts as sufficient, so do not assume that only a full migration rehearsal will do.
- What scenarios must the plan cover?
- Provider failure, deterioration of service quality, business disruption from inappropriate or failed provision, persistent unforeseen interruptions, unexpected termination, and termination on any of the grounds in Article 28(7).
- Does DORA set a minimum transition period?
- No number is set. Article 30(3)(f) asks for an adequate transition period that allows migration to another provider or to in-house solutions and is consistent with the complexity of the service.
- Do small payment institutions need an exit plan?
- Article 28(8) has no size exemption. Exempted payment institutions and exempted e-money institutions follow the simplified ICT risk framework of Article 16 and are outside the written third-party strategy and policy duty of Article 28(2), and proportionality applies to how much testing is sufficient.
Sources
- Regulation (EU) 2022/2554 (DORA), Articles 28, 30 and 31, on EUR-Lex
- Commission Delegated Regulation (EU) 2024/1773, RTS on the policy on contractual arrangements, Article 10 (exit)
- Commission Implementing Regulation (EU) 2024/2956, register of information templates, Annex I (B_07.01, B_02.02)
- EBA Guidelines on outsourcing arrangements, EBA/GL/2019/02, section 15 (exit strategies)
- EBA, final report on Guidelines on the sound management of third-party risk regarding non-ICT services, EBA/GL/2026/09 (18 September 2026)
- FINMA Circular 2018/3 Outsourcing, margin no. 18.1
Read next
Discuss how this applies to your institution with the Finray team.
Book a briefing